Delayed SYNC response on FarmaFlux services Solved

Start date:
08/08/2022 - 10:30
End date:
08/08/2022 - 11:50
Lead:
APB
Description:

Since 10H25, FarmaFlux Servcies experienced issues.  Impact on the field is a delayed response time for GFD-DPP requests and the registration of the RaTG tests.  The issue is stablised at about 11H50. 
Case closed

Impact:

Environment: Production

Services impacted: 

GFD-DPP:  consultation experienced a delay.  Registration is OK.

 ASSURPHARMA:  no trace of impact observed

 RaOTD:  Registration is OK.

  Vaccinnet Registration:  potential delay could have been observed

  RATG Regustration: potential delay could have been observed